4-22-08

High School Addition

All MEP rough-ins are scheduled for completion on May 2nd. Cable trays are 100% complete. Pulling electrical wires and data cables for the first floor are 100% complete. Ceiling grid for the First Floor started on April 7th. Ceiling grid for the second floor began the week of April 21st. Pulastic flooring for the multipurpose area is scheduled to start week of April 28th. VCT flooring for the Classrooms on the First Floor also is scheduled to start week of April 28th.

Junior High School

Roof trusses/purlins for the Cafeteria (Area A) are 100% complete. Insulation and roof panels for the gym (Area B) are 100% complete. Insulation and roof panels for the Cafeteria (Area A) are 25% complete. Trusses for the North Classroom Wing (Area D) are 100% complete. Trusses for the South Classroom Wing began April 21st. Brick started on April 7th and will be an ongoing process for the next 3 months.

Intermediate School

Cutting the building pad was completed on April 21st. Lime stabilization and building pad compaction began on April 22. Footers, foundations, and underground utilities are scheduled to start April 28th. The groundbreaking ceremony for the Intermediate School will be held Thursday, April 24 at 7 p.m.