4-9-08

High School Addition

Non-load Bearing CMU Walls are complete. 1st Floor MEP above ceiling rough-ins for the North and East Classroom Wings (Areas A & B) are complete. 2nd Floor MEP above ceiling rough-ins are 90% complete. Cable trays for the 1st Floor started on 03-28-08. Pulling electrical wires and cables for the first floor is 90% complete. Ceiling Grid started the week of 04-07-08. Air Handling Unit No. 8 (MP Room) was up-and-running on March 13th. Ceiling pads in the MP Room (Area C) are complete.

Junior High School

Roof trusses/purlins for the gym (Area B) are complete. Roof trusses/purlins for the cafeteria are 90%. Roof panels for gym started on 04-01-08. Kitchen (Area A) was poured on 03-12-08. Truss bearing CMU walls for North Classroom Wing (Area D) are 100% complete. Truss bearing CMU walls for South Classroom Wing (Area C) are 100% Complete. Pre-cast planks for mechanical rooms at the North and South Classroom Wings were set on 03-24-05. Trusses for the North Classroom Wing were delivered on 04-04-08. 2nd Floor above ceiling rough-ins started the week of 04-07-08.

Intermediate School

Notice to Proceed was issued to all contractors on 03-24-08. Mobilization took place the week of 03-31-08. Layout, footers, foundations, and underground utilities are beginning.