High School Addition The metal roof on the East Classroom Wing (Area B) is scheduled to be complete by January 25th. The metal roof on the North Classroom Wing (Area A) is scheduled to be complete on January 31st. Brick is 100% complete and windows/storefronts are 75% complete. First floor MEP above ceiling rough-ins for the North Classroom Wing (Area A) are completed. First floor MEP above ceiling rough-ins for the East Classroom Wing (Area B) are scheduled to start February 1st. The first coat of paint is completed in the Multi-Purpose Room (Area C). All basketball boards are hung in the Multi-Purpose (Area C), and ceiling grid started January 21st.
Junior High School First floor above ceiling rough-ins are 95% complete in the Locker Rooms (Area B). Second floor CMU bearing walls for Art/Technology rooms (Area B) are completed. Slab-on-Metal Deck for South Classrooms (Area D) was poured on January 11th. First floor above ceiling rough-ins in South Classrooms are 10% complete. Bar Joists/Metal Decking for North Classrooms (Area C) is 75% complete. Slab-on-Metal Deck is scheduled to be poured the week of January 28th. CMU bearing walls for Kitchen/Cafeteria is completed. Roof trusses for Gym and Kitchen/Cafeteria (Areas A & B) are scheduled to start the week of January 28th.
Intermediate School
Meter Pit was installed the week of January 14th. Contract Documents went out to bid on January 18th, and a pre-bid meeting is scheduled for January 31st.