1-8-08

High School Addition

Veneer brick on the North Classroom Wing (Area A) is complete. Interior non-bearing CMU walls are 50% complete in the North Classroom Wing (Area A) and East Classroom Wing (Area B). All Air-Handling Units are set. Brick will be complete the week of January 14th. Trusses/Purlins are scheduled to be complete the week of January 7th. Roofing/Insulation started December 17th and will be completed by the end of January. Double Doors were added in the existing classroom by the cafeteria for future table storage. Ceiling Grid for the multipurpose room began January 7th.

Junior High School

Slab-on-Grade was poured in the Administration Octagon Area and the Music Room Area on December 18th. Slab-on-Grade in the Kitchen (Area A) is scheduled for January 9th. Bar Joist/Decking was completed the week of December 31st in the Southeastern Classroom Section (Area D). Slab-On-Deck placement for the Southeastern Classroom Section began January 7th. Above Ceiling Ductwork and HVAC Piping are 50% complete in the Locker Rooms (Area B). Ductwork and HVAC Piping is scheduled to start January 15th in the Southeastern Classroom Section (Area D).

Intermediate School

Final Grading on the early site work continues. The Board of Education will vote to go out for bid in January.