High School Addition
Pre-cast Planks for Mechanical Rooms were set on November 16th. Brick is 90% complete for Area A (North Classroom Wing). Brick for Area B (East Classroom Wing) is 20% complete. Above Ceiling Rough-ins are 50% complete in Area A (North Classroom Wing). Trusses/Purlins are 60% complete. Roof/Insulation started November 29th and instalation of the metal roof is scheduled to begin the week of December 10th.
Junior High School
Load bearing walls for the gym are completed to Truss Bearing. The remaining load bearing walls for the 1st floor are 75% complete. Pre-cast Planks were set on November 16th in Area B (Locker Rooms). Slab on Grade in the Media Center was poured November 30th. Slab on Grade for the Administrative Octagon and Music Rooms are scheduled to be poured the week of December 18th. Bar Joists/Decking started on December 3rd in Area D (Science/Classrooms). Brick is scheduled to start at the end of December.
Intermediate School
Meter Vault was installed on November 28th. Final Grading is 75% complete. Security/Construction Fencing was completed on December 4th, and Erosion Protection started December 3rd.