11-19-07

High School Addition

Load Bearing Walls are 100% complete. Roof Trusses in Area A were completed November 12th, and trusses in Area B started November 12th and are scheduled for completion on December 7th. Brick started in the Court Yards for Area A on November 5th. Roof/ Insulation is scheduled to start November 26th. The Multi-Purpose Vestibule opened on November 3rd for public traffic. HVAC ductwork started November 5th in the Multi-Purpose Room with a completion date of November 16th.

Junior High School

Exterior and Interior Load Bearing Walls in Area B (Gym/Locker Rooms) are complete. Slab on Grade in the Gym was poured on November 7th. Exterior and Interior Load Bearing Walls in Area D (Science/Classrooms) are 100% complete. Exterior Load Bearing Walls in Area C (Administration/Classrooms) are 70% complete, and Interior Load Bearing Walls in Area C started November 15th. Slab on Grade in Area C is 50% complete with the remainder scheduled for the week of November 26th. Foundations and Footings are 95% complete in Area A (Kitchen/Cafeteria).

Intermediate School

Paving was completed on November 9th. Seeding started November 8th and is expected to be complete the week of November 26th. Final Grading and spreading top soil started the week of November 5th. Installation of Rip Rap and Head Walls will start week of November 19th. Meter Pit installation will start the week of November 26th.