HIGH SCHOOL ADDITION
Second Floor (North Wing Addition) Load Bearing Walls were completed October 23rd. Second Floor Area B (East Wing Addition) Slab on Deck was poured on October 13th. Second Floor Area B Load Bearing Walls are 75% complete. Roof Trusses for Area A are scheduled to start the week of November 12th. Roof and Insulation for Area C (Multi-Purpose Room) is scheduled for completion on November 2nd. Sidewalks for Area C started on October 25th and will be completed by November 1st. Vestibule for the Multi-Purpose Room will be completed on November 2nd. The public will have full access through the vestibule by the gym for basketball season on November 5th.
JUNIOR HIGH SCHOOL
Footers and Foundations for Area B (Gym/Locker Rooms) & Area D (Classrooms) are complete. Footers and Foundations for Area C (Administration/Classrooms) are 75% complete. Slab on Grade for the Locker Rooms in Area B was poured on October 16th. Slab on Grade for Classrooms in Area C was poured on October 30th. The remaining Slab on Grade for Area D is scheduled to be poured the week of November 5th. Load Bearings Walls for Area B and Area D are 75% complete. Load Bearing Walls for Area C are 30% complete
INTERMEDIATE SCHOOL
Final Grading for Site and Paving Areas started October 22nd. All Utilities are complete up to 5 feet of the building. Water Meter is scheduled to be complete the week of November 12th. Seeding and Asphalt Paving are scheduled to start week of November 5th.