HIGH SCHOOL ADDITION
For the North Wing Addition, all the Bar Joists and Decking are complete with the slab on deck poured on October 6. Second Floor Load Bearing Walls were started on October 8th and are scheduled to be complete by October 19th. Roof Trusses are scheduled to start the week of October 22nd. In the East Wing Addition, the first floor Load Bearing Walls were completed on October 5th. Bar Joists and Decking started on October 8th and will be complete by October 16th. Slab on Deck is scheduled to pour on October 17th with the second floor Load Bearing Walls to follow. Site Demo was completed on October 9th for the Multi-Purpose Addition. The Entry Way Slab for the Vestibule is poured, and the Sidewalks are schedule to start week of October 15th. Fireproofing for the Vestibule is completed, and the Above Ceiling Mechanicals, Ceiling, Store Front, and Entry Way Mats are underway to be finished by November 2nd and Open for the Basketball Season starting November 3rd.
JUNIOR HIGH SCHOOL
Footers and Foundations for Area B & D (Gym/Locker Rooms Area & Classroom Area) are complete. The Equipment Elevator Shaft Walls are poured, and the Concrete Slab is poured for the Classrooms in Area B. Footers and Foundations for Area C (Administrative/Classrooms) are 50% complete, and Footers and Foundations for Area D (Cafeteria/Kitchen) are 30% complete. The Locker Room Area is being prepared for a Concrete Slab pour around October 17th. Exterior Load Bearing Walls for Area B & D are 95% complete, and Exterior Walls for Area C are 30% complete.
INTERMEDIATE SCHOOL
The Building Pad is complete and proofed rolled. Trees have been removed from Zoar & Stephens roads. The Sanitary and Storm Sewer are 100% complete, and the Site Rough Grading is completed up to plus/minus 1'-0"