9-12-07

High School Addition

The North Side (Area A) concrete slab was poured on August 23rd in the Classroom Wing. The first floor Load Bearing Walls are 70% complete and scheduled to be finished the week of September 17th. The slab on grade prep work is 50% percent complete on the East Side (Area B). Slab on Grade is scheduled to be poured on September 14th. The bar joists and decking are 90 percent complate for the Multi-Purpose Room. The Vestibule Slab is formed up and schedule to be poured on September 14th.

Junior High School

The Notice to Proceed was issued on August 24th. Contractors mobilized the following week with excavation and pouring of footers beginnng September 4th.