8-23-07
Little Miami High School Addition
In the Classroom Wing Addition, exterior∫walls and door frames began on the east side. All the stone sub base is in the foundation, and vapor barrier is completed on the north side. All trench block outs have been installed. The north side concrete slab was poured on August 23rd. For the Multipurpose Room, brick is 100% complete. Pre-cast planks are schedule to be installed the week of August 27th. Bar Joists and Decking has started and scheduled to be complete week of September 4th.
Little Miami Junior High School
The base asphalt course for parking lot and drive is 100% complete. Seeding is 70% complete. Junior High School building pad is at final sub grade elevation and ready for the General Contractor to start footings and foundations. The Groundbreaking Ceremony was on August 22nd, and the Little Miami School District was the first to break ground on the New Junior High School.