PROJECT UPDATE

8-9-07

Over the last several weeks, the Early Site Contractor completed the underground plumbing outside the new Junior High School building pad. The underground electrical work was completed the week of July 31, and the gas line will be completed during the week of August 13. The Junior High School building pad is at final sub grade elevation and is ready for the General Trades Contractor to start the footings and foundations. The parking lot and drive received its final grading, and the stone sub base has been installed, ready for the base course asphalt, which is scheduled to start the week of August 13.

New photos have been added to both the Junior High School and High School Additions web pages.